Progress on world’s first artificial energy island revealed

QAZAQ GREEN. Construction of the world’s first artificial energy island, that will serve as an energy hub for collecting and distributing renewable energy from offshore windfarms, is well underway in the Belgium North Sea, Rivieramm reports.

Milestones in building the massive Princess Elisabeth Island, some 45 km off the Belgian coast, were discussed by expert panellists during a session at IPF 2024 In New Orleans held in April. The first construction contract for the EU-funded artificial island project was awarded last year to TM Edison, a consortium made up of the Jan De Nul Group (JDN Group) and Deme Group.

Panellists at IPF 2024 detail challenges of building massive Princess Elisabeth Island.

Panellist JDN Group senior business development manager, Carl Heiremans, said the project would require building 23 caissons, or foundations, that will form the outside walls of the artificial island.

Each concrete caisson weighs about 22,000 tonnes and takes about three months to build at a facility in Holland. The construction process involves five separate phases which take about 20 days each to complete, according to electricity grid infrastructure operator and developer Elia Group.

The first of the island’s caissons has almost been completed and will be transported by sea and installed on the seabed later this year. Located in about 18 m of water, the island will have a seabed footprint of about 25 hectares and around seven hectares on the surface.

“You are less exposed on the energy island”

Princess Elisabeth Island will connect to secondary wind zones, and in the future, will serve as an interconnector with the UK and Denmark. The island will act as an offshore energy hub, collecting high-voltage alternating current (HVAC) electricity generated by offshore windfarms in the Princess Elisabeth Zone, and send high-voltage direct current (HVDC) back to shore via subsea cables. With a capacity for up to 3.5 GW of offshore wind power, the island will facilitate the exchange of renewable electricity between European countries.

Building an artificial island allows for higher availability and easier maintainability than a floating substation, panellists pointed out. Additionally, Mr Heiremans noted: “You are less exposed on the energy island” to allow crews to safely maintain the energy infrastructure. He said the island also offers “much higher modularity to allow for build out.” Modularity is vital to allow for expansion and future proofing. Another consideration in the design was making the artificial island environmentally friendly to attract birds and sea life. He said construction of the island should be completed by 2026.

Mr Heiremans was joined on the panel by Blauwe Cluster chief executive Piet Opstaele, e-Bo Enterprises international business development renewables Vincent Dehullu, KU Leuven research expert Hakan Ergun and Wind Grid chief executive Markus Laukamp.

Energy security and resilience is driving the construction of Princess Elisabeth Island. One of the largest offshore wind developers in the world with about 2.26 GW of capacity, Belgium has joined with eight other European countries, Denmark, France, Germany, Ireland, Luxembourg, the Netherlands, Norway and the UK, in signing the Ostend declaration to develop 120 GW of offshore wind in the North Sea by 2030, and 300 GW by 2050.

24.04.2026
CAREC and Central Asian universities sign new memoranda on green skills development
24.04.2026
100,000 jobs and a skills gap: how Central Asia is preparing for the renewables boom
24.04.2026
No transition without transmission: How Central Asia is building its energy future
23.04.2026
ADB to invest $5.5bn across 15 projects in Kazakhstan
23.04.2026
17 agreements worth over $2.3 billion signed at the opening of RES 2026 EXPO in Astana
22.04.2026
World Bank to invest $1bn in Central Asia's energy integration
22.04.2026
Kazakhstan and China to launch a 500 MW wind farm in Karaganda region
22.04.2026
Kazakhstan and Tajikistan move toward clean power deal over Rogun HPP
22.04.2026
Regional Ecological Summit 2026 opens in Astana
21.04.2026
Solar pumps and drip irrigation help Kyrgyz farmers cut costs amid rising energy prices
21.04.2026
Hormuz closure failed to trigger coal comeback as solar and wind filled the gap
20.04.2026
Astana set to launch RES 2026 EXPO and ink key international deals
20.04.2026
Central Asian countries to discuss energy transition at RES 2026 in Astana
20.04.2026
Moldova surpassed 1 GW of installed renewable energy capacity
20.04.2026
China begins building US$1 billion hydropower station in Cambodia
20.04.2026
Thousands protest in Germany urging faster green shift
17.04.2026
Scientists from Russia and Uzbekistan improved the stability of green energy systems by 24%
17.04.2026
Kazakh startup ranks in GCIP global top 3 in Vienna
16.04.2026
Kazakhstan poultry farm produces 15 million kWh of energy from waste
16.04.2026
China, Spain expand partnership in solar and wind power